Case Study

1. Office Space Building

A 2 Million sqft office building with 4 Common Basement and 2 Separate office tower. HSS BIM has developed the LOD 300 to LOD 500 Architectural, Structural & MEP BIM model.

  • Total No of RFI – 95 no’s
  • Total No of Clash report – 540 no’s
  • Value Engineering – Visualization, Space planning, Logistic planning

2. Hotel Project

A 1.3 Million sqft built-up areawith Basement and 55 story hotel block. HSS BIM has developed the LOD 300 to LOD 500 Architectural, Structural & MEP BIM model and extracted the Quantities at LOD 300 stage.

  • Total No of RFI – 110 no’s
  • Total No of Clash report – 390 no’s
  • Value Engineering – Visualization, Space planning, Logistic planning

3. Metro Rail Project

HSS BIM team has developed the BIM model for 24 Elevated Stations, 6 Underground stations and 2 Depots. The Scope is to develop the LOD 300 Architectural, Structural & MEP BIM model and develop the Construction Simulation.

  • Total No of RFI – 25 no’s
  • Total No of Clash report – 40 no’s
  • Value Engineering – Visualization
  • Construction Simulation – Input to the Contractor in the Schedule sequence and missing items.

4. Township/Smart city

A 2,500 acre smart city development project, as an initial stage the infrastructure BIM model is developed for the entire area with the Underground utilities and Internal roads. HSS BIM scope is to develop the LOD 200, LOD 300 BIM model, Coordination & Quantities.

  • Total No of RFI – 180 no’s
  • Total No of Clash report – 1880 no’s
  • Value Engineering – Visualization, Early identification of miss match in the different discipline levels.